1 Avenue Van Horne: A Century Between the Tracks and the Rules
The story behind the 1 Avenue Van Horne building, Mile-end, Montreal.

1 Avenue Van Horne
Site: Entrepôt Van Horne / Van Horne Warehouse, 1 avenue Van Horne, Montréal
Arrondissement: Le Plateau-Mont-Royal, at the tri-border with Rosemont–La Petite-Patrie and Outremont
Neighbourhood: Mile End — north edge
Executive Summary
A 1924 concrete-and-brick warehouse. Seven storeys, nearly windowless, crowned by one of Montreal's last steel water towers. It was built to move freight between the Canadian Pacific rail line and the road network — and now, a century later, it's the last unconverted industrial monolith on a block that has converted everything around it.
The parcel tells a story of a single unbroken use — storage, 1924 to 2022 — that outlived its economic logic by thirty years. The block tells of Mile End's post-1990 mutation from garment-and-rail district to artist enclave to Ubisoft-and-Mile-Ex tech corridor. The city ring shows the PUM 2050 designating the building an exceptional heritage industrial ensemble inside an employment zone where, after Lac-Mégantic, housing beside the rail line is off the table.
The gap being priced today: a vacant document depot versus an authorized floor-space ratio of 6.5[1], with a hotel of about 120 rooms, a guaranteed minimum of 25% artist studios, ground-floor retail, a rooftop greenhouse, and a new four-storey office building next door at 55 Van Horne. The enabling règlement — P-25-021, adopted under article 89 of the city charter — received a favourable report from the Office de consultation publique de Montréal (OCPM) in December 2025[2] and was scheduled for adoption in winter 2026; as of October 2026 we have not found a council vote adopting it.
6.5
Maximum floor-space ratio at 1 avenue Van Horne under draft by-law P-25-021

The Site
The subject parcel — 1 avenue Van Horne, lot 1 867 998 of the Cadastre du Québec — sits in the Plateau-Mont-Royal, governed by Règlement d'urbanisme 01-277. It has been vacant since 2022 and is the object of draft règlement P-25-021.
The attached parcel — 55 avenue Van Horne, lot 2 135 975 — holds a one-storey building slated for demolition and replacement by a contemporary four-storey office building. Same owner, Rester Management, same règlement.
To the west sits the Jardin du Crépuscule, a sculpture garden created by local artist Glen LeMesurier, which consultation participants flagged as at risk from construction and the planned parking ramp. To the north, the active Canadian Pacific rail corridor — the constraint that killed residential use on this site. To the south and east, the Rosemont–Van Horne viaduct and the Saint-Laurent tunnel; the City plans a transformation of the viaduct by 2030, with no public plan yet available.

The Parcel
Site and Ownership
The lot is an irregular sliver bounded by the CP rail line to the north, the Saint-Laurent tunnel to the east, avenue Van Horne to the south and the Saint-Urbain underpass to the west.
The ownership chain, per Héritage Montréal's heritage record: built for Wilfrid Duquette's St. Lawrence Warehousing Company, which remained owner until the early 1960s[3], when it passed to Van Horne Warehouse Inc. Press coverage (Le Devoir, 2025) reports that Rester Management acquired the building in 2019 — though there's a genuine conflict in the record: Le Devoir's 2022 reporting described Rester as owner "for about ten years," and Héritage Montréal describes both the 2013 proponent and the 2023 proponent as "a new owner." The sale dates, prices, and the identity of the 2013-era owner sit in the Registre foncier du Québec, which is paywalled; nothing here is drawn from it. The assessed value and matricule from the rôle d'évaluation were likewise not pulled in this pass.
Origin Story
The building went up in 1924–1925 on land whose entire logic was the railway. The avenue itself is named for William Cornelius Van Horne, the CP president who drove the transcontinental line; the Mile End station at Saint-Laurent and Bernard had made this stretch an industrial magnet since the 1890s.
Wilfrid Duquette, a warehousing entrepreneur, built the seven-storey structure for his St. Lawrence Warehousing Co., replacing an earlier two-storey store-warehouse — a bet that the crossing of rail and road here was worth a monolith. The large ground-floor openings on both sides, bricked up since shipping containers arrived in the 1950s, recall its original role as a transshipment station between the rail and road networks. The small upper openings testify to its warehouse function. The steel water tower on the roof is a vestige of the fire-suppression system, decommissioned in 1992 and one of the last in the city.
The workforce context: the east side of the tracks was working-class Mile End, annexed to Montreal (as Ville Saint-Louis) in 1910, its economy stitched to the garment factories and freight yards along the CP line. The original architect is not identified in the public records pulled — the 1924 permit card at the Archives de Montréal would name the designer.
Build Potential
Under the Plateau's Règlement d'urbanisme 01-277, the building is listed as a témoin architectural significatif (Annexe B). What's precisely documented is the authorized envelope under draft règlement P-25-021: a maximum floor-space ratio (COS) of 6.5 for 1 Van Horne and 4.6 for 55 Van Horne[1]; a maximum height of 23.2 metres for both buildings, with the water tower, greenhouse, mezzanine and rooftop equipment excluded from the calculation; a mandatory minimum of 25% of floor area at 1 Van Horne for artist and artisan studios; and the hotel capped at 50% of the complex. The project itself plans about 120 rooms and 50 underground parking spaces; those are the proposal, not by-law limits.
| Rule | 1 avenue Van Horne | 55 avenue Van Horne |
|---|---|---|
| Maximum floor-space ratio (COS) | 6.5 | 4.6 |
| Maximum height | 23.2 m | 23.2 m |
| Excluded from height | Water tower, greenhouse, mechanical penthouse, stairwell and other rooftop elements | The same exclusions |
| Artist and artisan studios | At least 25 % of floor area | — |
| Hotel | At most 50 % of the complex | At most 50 % of the complex |
| Start of construction | Within 60 months of entry into force | Within 60 months of entry into force |
For contrast, here is what Bucky's saved analysis reads from the zoning in force today, before any by-law:
What the zoning allows
Van Horne warehouse, Mile End
1 Avenue Van Horne, Montreal, QC · Le Plateau-Mont-Royal
- Floor area ratio
- 3
- Maximum height
- 20 m
- Maximum stories
- 5
- Maximum site coverage
- 100 %
- Maximum floor area
- 6,109 m²
- Maximum footprint
- 2,036 m²
- Rear setback
- 3 m
- Side setback
- 2.5 m
Saved analysis from October 12, 2026.Open in Bucky
The delta here is unusual: the existing building already fills most of that envelope. The value gap is not unbuilt density but unusable density — seven floors of dark storage space versus 6.5 COS of authorized commercial use. To get there, the proposal derogates from roughly a dozen provisions of 01-277, covering height, density, permitted uses, mezzanines, awnings, mechanical equipment, parking and café-terrasse rules.
Physical Constraints
The constraints are the story of this parcel.
Structural: a May 2021 preliminary structural report found a major renovation "entirely feasible" but flagged the frame and seismic capacity; an April 2023 lateral-resistance expertise concluded the existing elements are insufficient as-is, though seismic upgrading is "achievable and viable."
Rail: the active CP line runs hard against the north wall. After the Lac-Mégantic disaster of July 2013, building housing this close to a rail line is no longer possible — a hotel or offices, however, are. This single constraint explains why every affordable-housing demand made in consultation was structurally impossible on this lot.
Openings: the building is essentially windowless, its walls three brick-rows deep, making fenestration the central architectural problem of any conversion.
Contamination: no listing was confirmed in this pass, but La Presse notes the building stored, over a century, milling products, chemical components, furniture and archival documents — the chemical-storage interval makes a check of the MELCCFP and municipal registries worthwhile.
Heritage: PUM 2050 lists the building as part of an "ensemble patrimonial industriel exceptionnel,"[1] and the OCPM has recommended the City adopt a citation under the Loi sur le patrimoine culturel — an intermediate legal status that frames future interventions while opening access to financial and technical aid.
Site Timeline
Happened: Built for Wilfrid Duquette’s warehousing company[3]
Seven storeys of concrete and brick beside the CP line; St. Lawrence Warehousing owned it until the early 1960s.
Happened: Rooftop water tower taken out of service[1]
Happened: Glass-façade conversion proposed[3]
A mixed commercial-residential project. Héritage Montréal put the building on its 2014 watch list, and the project went no further.
Happened: Rester Management acquires the building
As reported in the press; the date and price are not confirmed in the land registry.
Happened: First application to the CCU: offices and a hotel[1]
The last tenants left in 2022; the building has been vacant since.
Happened: Borough survey closes[4]
10,732 respondents; 74 % disagreed with offices and a hotel in the building.
Happened: Favourable CCU opinion, with conditions[5]
Happened: Favourable opinion from the Conseil du patrimoine and the Comité Jacques-Viger[1]
Happened: Council adopts draft by-law P-25-021 and mandates the OCPM[6]
Under article 89 of the Charter, which replaces a referendum with a public consultation.
Happened: OCPM report recommends adoption[2]
331 written contributions. It also recommends a heritage citation for 1 avenue Van Horne.
Happened: OCPM report tabled at city council[7]
Expected: Final adoption and entry into force[5]
The City scheduled it for autumn 2025–winter 2026. As of October 26, 2026 we have not found a council vote adopting it.
74 %
of 10,732 survey respondents disagreed with having offices and a hotel in the building (59 % strongly)
The city's schedule had the by-law adopted and in force by winter 2026; construction must then begin within 60 months. The OCPM report reached council on January 26, 2026. We have not found a later vote.
The Block
Neighbouring Applications and Approvals
The immediate block's only active file is the subject complex — 1 and 55 Van Horne under one règlement. The consequential neighbouring "application" is public: the City's planned transformation of the Rosemont–Van Horne viaduct by 2030, for which no plan or budget yet exists — an unresolved variable both promoter and borough admit will reshape the site's access and public realm.
Who's Active Here
Named actors, from public records: Rester Management (owner and promoter); Thomas Balaban (architect) and Zébulon Perron (designer), both Mile End-raised; Les Ateliers Belleville (LAB), the nonprofit studio operator bound by a letter of intent summarized in December 2024, partnered with AU/LAB for the rooftop greenhouse; Glen LeMesurier, sculptor of the adjacent Jardin du Crépuscule; Héritage Montréal (Dinu Bumbaru) and Mémoire du Mile End (Justin Bur) as the heritage interlocutors; engineering by Poincaré ingénierie and RJC Ingénierie; borough politics carried by councillor Marie Plourde and, post-election, mayor Cathy Wong.

The Turn
Two candidates, one block-scale and one policy-scale.
Block-scale: the 2013 glass-façade proposal — the moment the building stopped being real estate inertia and became contested ground. Héritage Montréal's 2014 watch-listing set the precedent that governs everything since: conversion yes, erasure no.
Policy-scale: Lac-Mégantic, July 6, 2013 — the same year — which removed housing from the possibility space and pre-wrote the answer to the loudest demand of both consultations.
The 2025 precedent now set for the block: an article-89 règlement trading heritage-sensitive design and a 25% guaranteed cultural floor for hotel-and-office density beside the tracks. Every rail-adjacent friche the comité mixte flagged for future requalification will negotiate against this template.
Block Timeline
1876–1911 — Mile End station era; CP purchases the line in 1882; the avenue is named for Van Horne; industry lines the tracks. The rail corridor sorts the district: factories and warehouses hug the line, triplex Montreal fills in behind.
1990s — Deindustrialization; large industries leave the neighbourhood and new uses appear. Cheap lofts fill with artists and studios; Mile End's cultural reputation is manufactured in exactly the kind of space the warehouse represents.
2000s–2010s — Ubisoft anchors the Peck Building; Mile-Ex and Marconi-Alexandra heat up north of the tracks; consultation testimony describes tech firms like Microsoft driving up land values in adjacent Mile-Ex, pushing out residents, shops and artists. The warehouse becomes the visible holdout — the same blind brick wall while everything around it re-glazes.
2013–2026 — The two conversion attempts, chronicled above; the under-viaduct informal culture — the skatepark, the raves, LeMesurier's sculptures, the nearby Champ des Possibles — becomes the counter-narrative in every consultation.
The City
Governing Plans and Intent
PUM 2050, adopted by city council in June 2025,[8] designates both lots "Activités diversifiées" — an economically dominant designation permitting commerce, offices, light industry, collective or institutional facilities and urban agriculture — and lists 1 Van Horne among heritage properties as an "exceptional industrial heritage ensemble."
The site also sits in the PDUES Marconi-Alexandra / Atlantic / Beaumont / De Castelnau territory (2013), whose non-binding orientations are to affirm the economic vocation, support mixed and diversified milieus, improve the urban landscape, and de-enclave the quartiers while improving mobility. The project is a near-literal execution of those four lines.
Policy Changes With Value Impact
Article 89 authorization route (↑): removes the referendum risk that hangs over any dérogation-heavy Plateau project; the borough explicitly evoked a process avoiding popular referendums in favour of public consultation.
Post-Lac-Mégantic rail-proximity restrictions (↑ commercial / ↓ social license): housing is excluded, so the highest permitted use — hotel and office — faces no residential-inclusion obligation, but the project absorbs continuous gentrification criticism for it.
Recommended heritage citation (↑↓): frames future interventions while giving access to financial and technical aid — constraint and subsidy in one instrument.
Artist-studio funding (↓ risk): the OCPM notes the City's existing studio-support program has expired[1] and recommends the City finance the studios and back a fiducie d'utilité sociale; until funded, the 25% cultural floor's affordability is a promise, not a mechanism.
Règlement pour une métropole mixte: not triggered — no residential component.
Incentives, Infrastructure and Decision-Makers
Transit is the weak ring: bus 161 on Van Horne (nearest stop about 250 metres away), bus 55 on Saint-Laurent and Saint-Urbain, and métro Rosemont more than 700 metres away by an unfriendly walk. The Réseau-Vert linear park and the cycling network touch the site, but the Saint-Laurent approach is perceived as particularly accident-prone. Permits are conditional on a cost-sharing infrastructure agreement between the promoter and the borough. Decision-makers by role: the borough mayor (Plateau), the borough urban-planning councillor, the Service de l'urbanisme et de la mobilité, and city council, which holds the article-89 pen.
City Timeline
2013 — PDUES adopted after OCPM consultation. The city formally names the rail-adjacent sectors as its next employment frontier. 2013 — Lac-Mégantic. Rail-side housing dies province-wide. 2025 — PUM 2050 adopted; project mandated to the OCPM on August 25. The new plan arrives just in time to be quoted on both sides of the hearing. November 2025 — Municipal election; the OCPM president's transmittal letter addresses a new administration counting on better collaboration between boroughs and central services. Winter 2026 — Scheduled adoption window. 2030 — Viaduct transformation horizon.
The Narrative Arc
It was built to stand between two networks. In 1924, Wilfrid Duquette put seven storeys of concrete and brick on a sliver of land where the Canadian Pacific tracks met the road, because in that Montreal, the fortune was in the transfer — boxcars on one side, trucks on the other, and the St. Lawrence Warehousing Company's name painted across the top. The walls were three bricks deep and almost windowless, because merchandise doesn't need a view.
What broke wasn't the building. It was the transfer itself. Shipping containers arrived in the fifties and the great rail doors were bricked shut. Industry drained out of Mile End through the eighties and nineties, and the warehouse fell back on the last thing a windowless box can do: it stored paper. Docu-Dépôt, then Docudata — archives for companies, in the decades when every archive was being scanned. The water tower was switched off in 1992. The business model expired slowly, and in 2022 the last tenants carried out the last boxes.
The long middle was the strange part: for thirty years, the most visible building in Mile End was also its emptiest, a red-brick paquebot looming over a neighbourhood that turned artistic, then expensive, all around it. A glass-façade conversion was floated in 2013 and beaten back. The tracks that built it now blocked its most obvious future — after Lac-Mégantic, no one could put homes that close to the line.
The turn came when Rester Management, the architect Thomas Balaban and, eventually, ten thousand consulted neighbours negotiated what a windowless monument is allowed to become: a hotel that can't be housing, studios guaranteed a quarter of the floor, a restored water tower, a public rooftop.
What it is now, in one sentence: a vacant, exceptional heritage shell holding 6.5 floors of authorized city per floor of land — the gap between what the ground holds and what the rules, as of this winter, finally allow.
Open Questions
- Who owned the building in 2013, and when and for how much did Rester Management buy it? The Registre foncier would settle it (2019 per most reporting; Le Devoir's 2022 "ten years" conflicts).
- The rôle d’évaluation foncière entry: matricule, assessed value and recorded floor area.
- The 1924 permit card at the Archives de Montréal, which would name the original architect and contractor.
- The MELCCFP and municipal contaminated-sites registries, checked against the reported chemical-storage years.
- The zone number and grid under 01-277, in the borough’s PDF annexes.
- Lovell’s Directory, via BAnQ, to date the Docu-Dépôt and Docudata years and recover mid-century occupants.
- Council minutes from 2026, to confirm whether by-law P-25-021 has been adopted and whether the heritage citation was started.
Where this research comes from
Provincial: Cadastre du Québec lot numbers via the OCPM report (1 867 998; 2 135 975); Registre foncier du Québec — not accessed (paywalled), gaps flagged.
Central Ville de Montréal: montreal.ca project page "Transformation de l'entrepôt Van Horne"; Plan d'urbanisme et de mobilité 2050 (affectation and heritage listing, cited in the OCPM report); PDUES Marconi-Alexandra, Atlantic, Beaumont, De Castelnau.
Arrondissement: Règlement d'urbanisme de l'arrondissement du Plateau-Mont-Royal (01-277), including Annexe B; CCU opinions (July 2022, April 2025); 2023 borough survey (Ad Hoc Recherche).
Consultative / para-municipal: OCPM, Rapport de consultation publique — Entrepôt Van Horne, December 19, 2025 (the primary document for this brief); avis préliminaire du Conseil du patrimoine de Montréal (February 7, 2025); avis du comité mixte CPM / Comité Jacques-Viger (June 17, 2025); énoncé de l'intérêt patrimonial (July 18, 2023).
Historical: Héritage Montréal, Memento — Entrepôt Van Horne; Échangeur Van Horne historical timeline (rail-era context).
Press: Le Devoir (September 2022; June 2025), La Presse (January 2023; February 2025), Radio-Canada (April 2023; January 2026), Le Délit (September 2025), EST MÉDIA Montréal (January 2026), Journal Métro (February 2023), Mon Plateau (June 2025), Voir vert (January 2026), URBANIA (September 2022).
Sources
- 1.
Rapport de consultation publique — Entrepôt Van Horneabcd
Published December 19, 2025 · Accessed October 26, 2026
- 2.
Entrepôt Van Horne — consultation file↩︎
Accessed October 26, 2026
- 3.
Accessed October 26, 2026
- 4.
Étude sur la transformation de l'entrepôt Van Horne (2023 survey report)
Accessed October 26, 2026
- 5.
Transformation de l'entrepôt Van Horne
Accessed October 26, 2026
- 6.
City council agenda, August 25, 2025 (item 43.01)
Published August 25, 2025 · Accessed October 26, 2026
- 7.
City council agenda, January 26, 2026 (item 07.04)
Published January 26, 2026 · Accessed October 26, 2026
- 8.
L'arrondissement de Ville-Marie adapte sa réglementation pour répondre aux orientations du PUM 2050↩︎
Published September 10, 2025 · Accessed October 26, 2026