A setback is the minimum distance a building must keep from a reference line, usually a property line. Zoning sets one for the front, the rear and each side, and a separate one for the street side of a corner lot. Together they draw a box inside the lot, and the building has to fit in it. The numbers change by zone, and in some cities they grow with the size of the lot.
Imagery: Esri World ImageryBefore projections and site exceptions. The setbacks leave 44% of this lot, less than the 50% coverage cap, so on this lot the setbacks are the tighter rule.
Every by-law names them a little differently, but the idea is the same.
Toronto defines rear and side setbacks from the lot line to the nearest main wall, measured horizontally at a right angle. Portland’s guidance also measures horizontally, not along sloping ground. So a steep lot does not get extra room, and the wall that sticks out furthest sets the distance.
From the front lot line on the street. Some cities let you match the average of your neighbours.
From the back lot line. Often the largest, to keep a backyard.
From each side lot line. Sometimes a single figure, sometimes a combined total for both sides.
The street side of a corner lot. Cedar Park’s General Business zone sets 7.62 m (25 ft), § 11.03.091.
Real lots, read from the by-law or ordinance. Same idea, very different numbers.
Live Bucky snapshots, October 2026. Lot areas from city parcel data. Corner-lot and flanking rules are not shown, because none of these four is a corner lot.
Subtract the setbacks from the width and the depth, then multiply.
Computed from the lot width and depth and the setbacks in the table above. Rectangular box only, before projections, exceptions and other rules.
A 40% cap on a 450 m² lot is 180 m², even if the box is 216 m². The live page works this example.
The box sets the footprint. Floor area ratio sets the total across storeys.
On Vancouver’s 10 m lot, the two side setbacks take 24% of the width.
Corner, flag, through and irregular lots rarely leave a clean rectangle.
Toronto and Vancouver set fixed metres. Chicago’s RT-4 rules are shares of the lot, so a deeper lot gets a deeper yard.
Rule text as stored in Bucky. This lot is 9.4 m wide, below the 10.7 m (35 ft) minimum frontage Bucky reads for the zone, so it is a legal question before it is a setback question.
The setback is for the main wall. Eaves, porches, decks and stairs often get their own, smaller limits.
Paraphrased from the toronto.ca consolidation of By-law 569-2013. Platforms must also keep their side clearances. Other cities use different numbers and some do not allow these projections at all.
They depend on the city, the zone, any overlays, the shape of the lot, the building type and any site exceptions. Look up the current zoning for the address and confirm the boundary with a survey before you rely on a distance.
No. The building must also stay inside the setbacks. How much you can cover and where you can put it are separate rules.
Close. Many codes call the open area between the lot line and the building a yard, and the minimum distance a setback. Read your code’s definitions, because they decide what can sit in the yard.
Move or shrink the building, or ask for relief: a minor variance in Ontario, a variance or relaxation elsewhere in Canada, or a variance from the board in the US. Relief from one setback does not waive coverage, FAR or height.
Bucky reads the front, rear, side and flanking setbacks for an address, with the section cited.